Guohong Guangdong Electric Guangdong Taishan Power Plant installation works of a 5 × 600MW # 5 unit

The engineering firm commitment to the 5 # Unit of the installation tasks, the contract was signed on September 20, 2004 from the boiler steel frame March 1, 2005 the first hook lifting, which lasted 21 months, passed on November 28, 2006168 hours of trial operation at the same time zero defect handover. All engineering data within a week 168 after the transfer is completed, the unit during the project construction by the State, the high evaluation of Heilongjiang Electric Power Company. And recommended as a model project of the National Thermal Power civilized construction.