1 X 330 MW Thermal Power Plant
CCCME
Member
- Product Details
- Company Profile
The EPC Contract of Phase II Expansion Project of 1 í 330 MW Thermal Power Plant, Uong Bi Vietnam was signed in Uong Bi City of Vietnam on April 11, 2008. Uong Bi Thermal Power Plant is the contract client and the finally owner of itself. The capacity o
The EPC Contract of Phase II Expansion Project of 1 í 330 MW Thermal Power Plant, Uong Bi Vietnam was signed in Uong Bi City of Vietnam on April 11, 2008. Uong Bi Thermal Power Plant is the contract client and the finally owner of itself.
The capacity of the project is one set of 330 MW thermal power generators. The Project EPC Contract was put into effect on May 4, 2008.
Project Progress:
- May 9, 2008 -- project group was dispatched to the job site
- May 23, 2008 -- the commencement ceremony of the project
- At the end of June 2008 -- the project kick off meeting in Chengdu
- July 2008 – first review meeting in the task force office in Longquan District
- August 2008 – second review meeting in the task force office in Longquan District
- Dec. 26, 2008 – first pilling ceremony at the job site
At the end of Dec. 2008, the general progress of the project was 19.8%, including: E – 48.3%, P – 23.7% and C – 2.5%.